Cut-to-Length AC36V Mining Strip: Drift Runs
A cut-to-length AC36V mining strip is ordered for a drift that grows every blast round. Here is how to survey it, build the cut list and take off the cuts.
Most cut-to-length AC36V mining strip orders leave a purchasing desk as one line: total metres, "cut on site", delivery date. On a finished tunnel that line is adequate. On a development drift it is wrong before the paperwork clears, because a drift is not a container with a fixed length of wall inside it. It grows by two or three metres every time the face is fired, and the lighting has to grow with it.
That changes what the buyer is actually ordering. Not a length, but a plan that repeats: a fixed part that can be built now, a variable part that has to be cut at the face, and a record that lets the next drift start from something better than a guess.
This guide works through the four things that decide whether a cut-to-length order fits a drift that keeps moving — the survey, the cut list, the take-off, and the log. It assumes the specification itself is already settled; if it is not, writing the AC36V mining strip specification is the page before this one, and the AC36V mining and tunnel lighting buyer's guide is the page before that.
Why a drift run is a length you cannot measure once
Two numbers set the pace of a development heading, and neither is a lighting decision.
The first is the round: the depth of hole drilled for one blast. In rock tunnelling it is chosen against the width of the opening, and a common working range across drift blast-design guidance is 0.5 to 0.7 times the tunnel width — a 5 m drift drills a round of roughly 3 m. The second is what actually comes down. Drilled depth is never fully realised: the practical advance per round in a development drift is normally 90 to 95% of the hole depth, and it gets worse as holes get longer because drilling deviation grows along the hole.
Put those together. A 5 m wide drift drilling 3 m rounds advances about 2.7 to 2.85 m per cycle. At two cycles a day on a five-day week, the face is roughly 5.5 m further on by the end of the day and about 28 m further on by the time the weekly report is written.

Above: the run as the cut plan sees it — equal factory pieces along the straight, shorter pieces around the turn, and one shaded piece at the face where the length is not yet known. Chainage, arc length and sealing class live on the sheet beside it, not on the drawing.
Three consequences follow, and each one is a line item.
A length measured at week one is wrong by week six. The measurement is not the deliverable. The deliverable is a rule for producing the next measurement, which is why the survey method in the next section matters more than any single number it produces.
The piece at the face is unknown by design. You know the run has to reach the face. You do not know, when the order is placed, exactly where the face will be on the day the strip arrives — the pull on that last blast is not decided until it is fired. A plan that pretends otherwise produces either a short run or an offcut nobody can use.
Total metres is a forecast, not a quantity. On a 400 m drift with a 3 m round, the gap between 92% and 88% pull does not show up in the metres — the drive is 400 m either way. It shows up in the cycles: about 145 blasts at 92%, about 152 at 88%. Seven more extensions if the lighting follows the face round by round, and seven more joints on the purchase order. Write the total as an estimate against a stated advance assumption, and let the cut plan carry the accuracy.
What the run is made of, in other words, is extensions. Each one is a piece of lighting sized to the ground gained since the last one, and the ground gained is the only dimension that is genuinely known at installation time.
Measure the route the way the strip will hang
Chainage is measured along the centreline of the drive. The drift lighting run length you actually need is a different number, because a strip is not mounted on the centreline: it hangs on a wall, or along the crown, at some offset from the survey line. On a straight drift the two lengths are identical to within a fixing tolerance. On a curve they are not, and the error is systematic rather than random.
A tape pulled tight across a turn under-reads. Pulled between two points on a curve, it measures the chord, not the arc. For a 90° turn the chord is 10% shorter than the arc — 9.97%, to be exact, and the percentage does not depend on the radius, because both chord and arc scale with it. A 45° turn under-reads by about 2.6%, a 30° turn by about 1.1%. So a drift that swings 90° into a crosscut, measured with a tape because the surveyor had already left, hands the installer a run that comes up 10% short at the far end. Tension the tape along the wall, or take chainage from the survey, and treat any taped curve as an underestimate.
The wall you mount on changes the length again. Add the lateral offset to the centreline radius and the geometry sorts itself out. A run on the inside of a curve is shorter than the centreline by the ratio (R − d) / R, where d is the offset from the centreline in metres:
Curve radius R | Offset d | Inside-wall path vs centreline | Outside-wall path vs centreline |
|---|---|---|---|
30 m | 1 m | 3.3% shorter | 3.3% longer |
20 m | 1 m | 5.0% shorter | 5.0% longer |
20 m | 2 m | 10.0% shorter | 10.0% longer |
10 m | 1 m | 10.0% shorter | 10.0% longer |
On main drives with 20 m and 30 m radii the correction is a few percent — small, but it lands on the same side every time, which is what turns it into a pattern of short runs rather than a nuisance. On tight radii around a shaft station or a loading bay it is 10%: a 90° corner at a 10 m radius carries 15.7 m of arc, and the strip on the inside wall needs 1.6 m less than that — which is exactly how a run ends up one piece short at the face.

Above: the two corrections in one view — the chord a tape measures across a turn, and the inner-wall path a strip actually takes. Both are shorter than the centreline arc, and on the same drift they compound.
Crown mounting is the exception. A strip hung along the roof keeps essentially the centreline length, because the offset is vertical and does not change the horizontal arc. That is one reason crown runs are easier to plan — and one reason they are not always the right answer, since the same height that simplifies the geometry moves the light away from the working face.
Arch and rib spacing set the joint grid. Whatever the survey says, a joint has to sit somewhere the strip can be fixed and later reached. On a supported drift that means the joint lands on or between ribs at the fixing interval, not mid-span where a strap has nothing to pull against. Record the rib pitch with the chainage; it decides where a cut is allowed to fall just as much as the electrical pitch does. Sections where the profile changes — a widening at a passing bay, a squeeze under a fall — are covered in mounting strip in irregular tunnel sections, and they belong on the same sheet.
The survey sheet that comes out of this has five columns: chainage start, chainage end, mounting offset and side, arc length at that offset, and a note on what is in between. Anything less and the person building the cut list is inventing the missing column.
From survey to a cut-to-length AC36V mining strip order
A tunnel LED strip cut list is not the order. It is the intermediate document that makes the order checkable — one row per piece, with the sealing class of each end decided before anybody picks up a knife.
From (chainage) | To (chainage) | Arc length at mounting offset | Ordered as |
|---|---|---|---|
0 + 000 | 0 + 010 | 10.0 m | Factory length, sealed both ends |
0 + 010 | 0 + 020 | 10.0 m | Factory length, sealed both ends |
0 + 020 | 0 + 030 | 10.0 m | Factory length, sealed both ends |
0 + 030 | 0 + 031 (face) | 1.0 m | Face allowance — 5 m delivered long, trimmed to 1 m at the face |
35 m ordered against 31 m installed: three whole factory lengths that need no cut at all, and one face allowance cut down once. The face piece is ordered at 5 m because that is the shortest length on the supply ladder which still leaves more than a full round of margin over the 1 m gap it covers — 5 m trimmed to 1 m leaves 4 m of allowance against a 2.7–2.85 m round. Four rules make those rows defensible.
The fixed end is factory-sealed; the moving end takes the cut. Every cut moves the sealing boundary, so the piece whose length is already known should arrive sealed and untouched. Only the piece that has to meet the face is a cutting job.
Order in supply increments, cut to the pitch. Those are different numbers and they are not derived from each other. A range may be supplied in 0.5 m, 1 m, 5 m and 10 m pieces while the cut pitch is something else entirely; assuming the smallest order length is also the shortest legal cut is the most common way a cut list fails at the face.
One allowance per run, at the face. Extensions are whole factory lengths. The single piece that has to meet the face is delivered long — a full round's advance plus a working margin — and trimmed on site. Size it from the gap, not from the ladder: the piece has to clear the face gap plus the round it must absorb, and the nearest supply length that covers the gap but leaves less than one round is not an allowance, it is a shortfall waiting for the next blast. One long piece is one cut. Margin sprinkled across every row is a cut on every row, and every cut is a seal.
Hold the row order. The list is installed in sequence from the fixed end, so the first row is the one that must not be wrong. If the count comes up short at the end of a shift, it should be short in the allowance, not in the run.
The worked version is dull, which is the point. Take a drift with 88 m of straight before a 90° right turn on a 20 m radius into a crosscut — 119.4 m of chainage — with the strip on the wall 1 m inside the turn. The centreline arc of the corner is 31.4 m; the inside wall takes 5% off it, so the strip needs 29.8 m round the corner and 117.8 m in total. In 10 m increments that is eleven sealed lengths and a twelfth carried as the face allowance and trimmed at the face to about 7.8 m — 1.6 m of chainage absorbed by the geometry, before the face has moved at all. That twelfth sits at the top of the ladder: 7.8 m out of a 10 m piece leaves 2.2 m of allowance, which is 0.5–0.7 m short of the 2.7–2.85 m round it exists to cover, and no single factory length in the range reaches the 10.7 m that would fix it. So a face that will fire again before the next delivery is planned with a shorter last increment rather than a longer piece: a 5 m length from 110 m to 115 m leaves a 2.845 m gap, and the same 10 m face piece then trims to it with about 7.2 m in hand — stock for the extension after that. A cut list of that shape can be quoted line by line; a total-metres order of the same drift cannot be checked at all.
Match each extension to the advance, not to the drawing
The drawing is a snapshot of a drift that was. The advance rate is what the order actually has to keep up with, and it is known early: contractors track metres per shift because they are paid on it.
So every cut-to-length mine strip order is really a run of these lines: each extension is a whole factory length, and the only piece carrying a written allowance is the one at the face. A 3 m round at 90–95% pull is 2.7–2.85 m of new ground per cycle; lighting extended every second cycle gains roughly 5.4–5.7 m, so the extension is a whole 10 m factory length cut back once at the moving end — the 4.3–4.6 m that comes off is a piece of lighting in its own right once it is cut back to a legal point, and it goes back to stock rather than into the bin. A 5 m length plus an offcut of the 0.4–0.7 m it is short also closes, if a spare that size is already on site. What does not close is a 5 m length trimmed: 5.0 m against 5.4–5.7 m leaves every second extension 0.4–0.7 m short of the ground it has to cover, and the shortfall compounds. Nothing is ordered at 5.6 m, and nothing gets a bespoke length per cycle.
Advance rate | Extension interval | Nominal increment | Practical order line |
|---|---|---|---|
2 rounds/day, ~2.8 m per round | Every 2 cycles | ~5.6 m | One 10 m factory length, cut back once to ~5.6 m |
1 round/day, ~2.8 m per round | Weekly, five working days | ~14 m | 10 m and 5 m factory lengths, one trim |
3 rounds/day, ~2.2 m per round | Every 2 cycles | ~4.4 m | One 5 m factory length, cut back once |
Two failure modes come out of getting this wrong, and both look like supplier problems. Order the whole drift's lighting at once and half of it sits in a store for six months, gets coiled and uncoiled, and arrives at the wall with a drawing that changed twice. Order only to the current face with nothing held long at the end, and every cycle ends in a cut at the worst possible place — which is the subject of the next two sections.
Where a cut is allowed to land
Inside a mine strip the LEDs sit in segments, and in strips built as regulated segments — the usual mains-driven arrangement — each section holds the current it needs, which is why brightness holds to the tail of a long run instead of fading along it, as long as the tail still sits above the regulator's minimum. A cut is legal where a segment ends. Everywhere else it is a destroyed section and a dark patch.
That makes the cut pitch — the interval between legal cut points — the single most important number in this whole exercise, and it is a property of the model, not of the category. Published figures from tunnel ranges vary enormously: one manufacturer states 10–15 cm intervals for their standard range, while consumer strips commonly quote 5 cm or 10 cm on 24 V reels. None of those numbers transfers to a different strip.

Above: a coil of silicone-jacketed mine strip. The repeating LED sections show through the jacket and the model marking is printed along one edge — on a frosted, dusty or wet strip that marking is often all you can read, which is why the cut pitch has to come from the datasheet rather than from the reel.
Mining strip cut marks are the second problem: on an IP68 strip the jacket is the seal, so the marks are often underneath it and invisible under normal light. Hold the strip against a bright background or read it from the back; if the marks genuinely are not visible, the pitch has to come from the datasheet rather than from the reel. Cutting where the mark probably is, on a strip that cost a day's production to install, is not a risk worth taking for the sake of a measurement.
The marginal piece is the other trap — and the reason a cuttable AC36V LED strip needs its pitch on the quotation rather than in a brochure. Cut between marks and the section past the last good pad stays dark: it is shorter than one segment, so it is not a piece of lighting, it is an offcut. The fix is not to cut more carefully; it is to move the cut back one pitch and accept a slightly shorter run. Every cut list should therefore carry the pitch for its model, so the person at the wall knows how much shorter is available.
If the supplier cannot state the pitch for the exact model in writing, the product has not been specified for field cutting, and no amount of care on site fixes that. That is a question for the quotation, not for the installation crew.
The 24 W AC36V mine strip shows the shape of that answer: IP68, white or RGB, supplied in 0.5 m, 1 m, 5 m and 10 m lengths and cut to length on site. What its product page does not give you is the cut interval, and that is the honest position for this model — the pitch, the connector class and the end-cap part are quotation items, because those three are what the field joint gets built from. A page that lists them is convenient; a supplier who will put them in writing is what makes the order checkable at all. When the far end of a run does go dim, it is usually a supply-length question rather than a cut one, which is a separate job to diagnose on site.
The take-off nobody quotes
A cut list is also a materials list, and the arithmetic is simple enough that there is no excuse for discovering it at the face.
Take one 100 m run, chained from pieces and fed from one end. The first piece takes the feed connection, every joint between pieces takes a connector pair, and the last piece takes an end cap. At three of the lengths this range is actually supplied in:
Mean piece length | Pieces per 100 m | Joints (connector pairs) | End caps | Feed connections |
|---|---|---|---|---|
1 m | 100 | 99 | 1 | 1 |
5 m | 20 | 19 | 1 | 1 |
10 m | 10 | 9 | 1 | 1 |
The pattern is the point: shorten the piece and the seal count climbs almost linearly. A run built in 1 m pieces has 99 joints in 100 m — 99 places where the IP claim depends on a person doing the same thing correctly. Split the same 100 m into five separately fed 20 m runs and the trade changes: fewer joints, five terminations, more cable. That is the real cost of a fine cut pitch, and it is paid in labour and seal integrity, not in strip.
And the connector has to be the right one. Pin count and width both have to match the model — a clip sized for 8 mm tape will not close on a 12 mm extrusion, and a four-pin coupling on a five-conductor strip leaves one core with nowhere to go. Order connectors against the model number rather than against "the strip", and count them from the joints column rather than from the metres.
Run length per power supply sets a ceiling on all of it: a cut list longer than one supply run is a second feed, not a longer strip. Where the take-off says 100 m and the feed design allows 60, the answer is two runs, two feed connections and an extra end cap — which is a sentence to write into the cut list, not a problem to discover while jointing.
Waste is smaller than most buyers assume, provided the pieces are long relative to the pitch. If every piece is cut back to the nearest legal point, the average offcut is half a pitch, so the waste fraction is the cut pitch divided by twice the mean piece length:
- 0.1 m pitch, 10 m pieces: 0.5% waste
- 0.5 m pitch, 10 m pieces: 2.5% waste
- 0.5 m pitch, 2 m pieces: 12.5% waste
Two conclusions follow. Fine pitches are cheap in strip and expensive in joints; coarse pitches are the reverse. And the spare metres should be carried as whole pieces plus a metre or two, not as a percentage — a 3% spare on 400 m is 12 m, which in 10 m increments is either one piece and a useless stub or two pieces, and the difference is a purchase order.
There is one asymmetry that decides the spare policy. A strip cut too short cannot be extended. It can only be jointed to another piece, which adds a seal in the middle of a run and leaves the offcut to be stored or binned. A strip cut too long can be cut again, at the cost of one more seal at the end. When the choice is between a longer piece and a shorter one, the longer one is the recoverable error — which is why the allowance belongs at the moving end.
Sealing the cut moves the IP68 boundary
An IP rating is a test result on one assembled enclosure, defined in IEC 60529 and summarised in the IP code. The factory can rate the length it built and tested. The moment that length is cut, the assembly that was tested no longer exists, and IP68 strip sealing after cut becomes a field procedure rather than a product property — re-earned through whatever connector, end cap and sealing method goes on the cut.

Above: the cut end of a strip and the end cap that goes over it. Everything past the cut is a field joint, and it has to re-earn the rating on its own — the factory tested a length that ended somewhere else.
Four things belong in writing before the first cut: the connector class and part, the end cap class and part, the re-sealing method, and who signs the joint off before the run is energised. "Sealed properly" is not a method, and an inspector cannot accept it. Factory-terminated lengths should be preferred wherever the cut list allows, precisely because the number on the datasheet is then the number on the wall.
Two boundaries are easy to confuse here. The first is voltage: AC36V sits inside the extra-low-voltage band as IEC 61140 defines it — not more than 50 V RMS alternating current between conductors or to earth — which is exactly why a drift runs on it. Cutting a de-energised 36 V strip is a low-energy operation; it is still a mains-derived circuit, and the isolation and lock-off discipline around it do not change because the voltage is low.
The second is protection. IP68 is ingress protection and nothing else. Where the drift is a classified hazardous area, the equipment needs approval under the regime that governs it — in US gassy mines that is MSHA approval under 30 CFR Part 18, identified by the approval plate on the equipment, and other markets run their own schemes. A cut-and-resealed strip is a modification of an approved assembly, which is a conversation to have with the approving authority before the cut, not after. What IP67 and IP68 actually cover is the rating side of the same argument.
Cutting to the advance: staging, transport and the 10,000 m proof
Once the run is planned as extensions, installation stops being an event and becomes a routine. Strip is added as the heading advances, in the same cycle as the services, and the lighting is never more than an extension behind the face. Progressive installation is standard practice on tunnel drives for the obvious reason: nobody wants to string 400 m of lighting through a drift that is still being blasted.
It also changes what you want delivered. Long factory lengths are efficient per metre and awkward per metre underground — a 30 or 50 m coil, the sort the tunnel and flexible models in the mine range are supplied in, needs room to be handled, uncoiled along the wall without dragging, and cut without kinking. Drift clearance above a services line is exactly where that room is scarce. There is a real trade between fewer joints (long pieces) and handling (short pieces), and the take-off table above is how you price it.
The scale version of the argument is a 10,000 m AC36V run in a South African underground mine. What that project demonstrates is not that strip can be made in quantity — it is that the distribution design was the straightforward part and the joints were not. Ten thousand metres of anything is a joint-management problem, and a joint management problem is what a cut plan is.
The as-built cut log, and the inquiry that produces it
The last document is the one nobody plans for and every maintenance team wants: a record of what was actually installed. It takes one line per cut and it answers the questions that come up eighteen months later, when a section goes dark and the drawing is three revisions out of date.
Record one line per piece, and record it while the installer still remembers which cut it was:
Chainage | Installed length | Termination at each end | Sealed by |
|---|---|---|---|
000.0 – 010.0 | 10.0 m | factory cap / joint | — |
010.0 – 020.0 | 10.0 m | joint / joint | RW, 14/03 |
020.0 – 030.0 | 10.0 m | joint / joint | RW, 14/03 |
030.0 – 040.0 | 10.0 m | joint / joint | RW, 14/03 |
040.0 – 041.2 | 1.2 m | joint / trimmed at face | pending |
Chainage at both ends, installed length, which termination went on each end, and the initials and date of whoever sealed it — plus the pitch the cut was measured against. Hand it over with the run. It is also the document that makes the next drift cheaper, because the next cut list starts from real installed lengths rather than a fresh guess.
Then the inquiry that produces all of it. What to send, and what to ask back:
Send | Ask back, in writing |
|---|---|
Site supply voltage and who owns the step-down | The cut pitch for the exact model |
Chainage list, mounting side and offset per run | The connector and end cap part for each cut |
Advance rate and rounds per cycle | The re-sealing method and who signs it off |
Rib or arch pitch and fixing pattern | Supplied lengths available against that pitch |
Hazardous-area classification, if any | Certificate number, marking and scope for the exact model |
Total metres as an estimate plus the advance assumption | Spare pieces and fittings, and who holds them |
Six lines out, six answers back, and the quotation you receive can be checked against a drift that is going to move. Ask for the cut interval and the sealing method first: without those two, a cut-to-length order is a length with a promise attached, and the promise gets tested at the face rather than at the factory.
We build the AC36V mine strip 24 W configuration at Pileds — IP68, white or RGB, supplied in 0.5 m, 1 m, 5 m and 10 m lengths and cut to length on site — and the cut interval, the connector and the end-cap part come back with the quotation, in writing, against the model you name. If you have a drift survey and half a cut list, send both to our engineers: what comes back is the six answers above, ready to paste into the request for quotation.
Specifying pixel LED for a real project?
Send the spec — pitch, IC, IP class, run length, voltage — and you get an engineer's answer, not a catalogue. Samples and OEM/ODM quotes from the Shenzhen factory floor.